Crosswalk Installation

Message

The schedule to install asphalt crosswalks is as follows:

Wednesday, July 18 7am – noon Install crosswalks at west side of Lake Street at Seehorn, Stout and W Maple Wednesday, July 18 noon -5pm Install crosswalks at east side of Lake Street at Seehorn, Stout and W Maple

Thursday, July 19 7am – noon Install crosswalks at South Dossett at JR Bell Thursday, July 19 noon – 5pm Install crosswalks at Seehorn behind Culp Center

Asphalt needs to cool before painting.

Friday, July 20 7am – noon Paint crosswalks at west side of Lake Street at Seehorn, Stout and W Maple Friday, July 20 noon – 5pm Paint crosswalks at east side of Lake Street at Seehorn, Stout and W Maple

Friday, July 20 7am – noon Paint crosswalks at South Dossett at JR Bell Friday, July 20 noon – 5pm Paint crosswalks at Seehorn behind Culp Center

Summers Taylor is to maintain two way traffic during the construction.

If you have questions or concerns, please call Facilites at 439-7900.